Upcoming:

Network Upgrade Project
McGregor Building access switch upgrade
Scheduled
Start: 24 Aug 2014 08:00 AM
End: 24 Aug 2014 08:00 PM
Cluster Witness Service
Duhig Building Power Works
For Information
Start: 27 Aug 2014 07:00 AM
End: 27 Aug 2014 07:30 AM
Data Centre
GPN Data Centre - Minor power work
For Information
Start: 29 Aug 2014 08:00 AM
End: 29 Aug 2014 04:00 PM
Active Directory
Active Directory OU Changes: TEDI/CIPL/CEIT
For Information
Start: 01 Sep 2014 05:30 PM
End: 01 Sep 2014 06:00 PM

Current & Recent:

Network Upgrade Project
Otto Hirschfield Building network and switch upgrade
Completed
Start: 23 Aug 2014 12:00 PM
End: 23 Aug 2014 08:00 PM
Building Networks
Distribution Router Upgrade
Completed
Start: 23 Aug 2014 09:00 AM
End: 23 Aug 2014 05:00 PM
Data Centre
GPN Data Centre - Minor power work
Resolved
Start: 22 Aug 2014 08:00 AM
End: 22 Aug 2014 04:00 PM
Building Networks
Network outage at OHC South and South Central
Completed
Start: 21 Aug 2014 10:00 AM
End: 21 Aug 2014 05:00 PM
SchoolsNet
Carrier outage affecting some schools
Resolved
Start: 21 Aug 2014 03:06 PM
End: 21 Aug 2014 03:58 PM
Kerberos Servers
Kerberos service patching
Completed
Start: 19 Aug 2014 05:00 PM
End: 19 Aug 2014 05:15 PM
Internet Services UQ
Internet Router Upgrades
Completed
Start: 17 Aug 2014 07:00 PM
End: 17 Aug 2014 09:00 PM
Exchange Mail and Calendaring
Central Exchange Mail Services
Completed
Start: 16 Aug 2014 09:00 AM
End: 16 Aug 2014 01:00 PM
Windows File Serving Ipswich
Ipswich File Serving Services
Completed
Start: 16 Aug 2014 09:00 AM
End: 16 Aug 2014 01:00 PM
Windows File Serving St Lucia
UQFILE File Serving Services
Completed
Start: 16 Aug 2014 09:00 AM
End: 16 Aug 2014 01:00 PM
SQL Cluster Database Hosting
SQL Database Services
Completed
Start: 16 Aug 2014 09:00 AM
End: 16 Aug 2014 01:00 PM
Data Centre
GPN Data Centre - Minor power work
Resolved
Start: 15 Aug 2014 08:00 AM
End: 15 Aug 2014 04:00 PM
Building Networks
Chemistry Building Lower Levels Network Outage
Resolved
Start: 15 Aug 2014 07:36 AM
End: 15 Aug 2014 09:54 AM
Building Networks
Michie Building Level 1 and 2 Network Maintenance
Completed
Start: 15 Aug 2014 07:00 AM
End: 15 Aug 2014 07:10 AM
Monitoring Servers
Prod/Dev Xymon monitoring service outages
Completed
Start: 12 Aug 2014 05:30 PM
End: 12 Aug 2014 06:00 PM
Building Networks
Switch upgrade
Completed
Start: 12 Aug 2014 07:00 AM
End: 12 Aug 2014 09:00 AM
Checkbox
Checkbox Survey System Upgrade
Completed
Start: 11 Aug 2014 07:00 PM
End: 11 Aug 2014 08:00 PM
PABX
Herston PABX reduced connectivity
Resolved
Start: 09 Aug 2014 06:00 AM
End: 11 Aug 2014 10:10 AM
Network Upgrade Project
Steele Building aggregation switch and access switch stack upgrade
Completed
Start: 10 Aug 2014 08:00 AM
End: 10 Aug 2014 08:00 PM
Building Networks
Distribution Router Hardware Maintenance
Completed
Start: 10 Aug 2014 09:00 AM
End: 10 Aug 2014 11:00 AM