Upcoming:

Internet Services UQ
Brief interruption to UQ Internet connectivity
Scheduled
Start: 19 Dec 2014 06:00 PM
End: 19 Dec 2014 07:00 PM
Voice Services
St Lucia Phone Service
Scheduled
Start: 20 Dec 2014 07:00 AM
End: 20 Dec 2014 08:40 AM
Echo360 Servers
Upgrade to Echo360
Scheduled
Start: 21 Dec 2014 05:00 AM
End: 21 Dec 2014 05:00 PM
Building Networks
Network outage at Level2 Physics Annexe (Part)
Scheduled
Start: 22 Dec 2014 05:00 PM
End: 22 Dec 2014 10:00 PM
The Raisers Edge
Raisers Edge Post Office File and Plug-in Updates
Scheduled
Start: 23 Dec 2014 06:30 PM
End: 23 Dec 2014 09:00 PM
Active Directory
Active Directory Organisational Unit Updates: January 2015
Scheduled
Start: 08 Jan 2015 05:00 PM
End: 08 Jan 2015 06:00 PM

Current & Recent:

OH&S Risk Management Website
OH&S Risk Management system upgrade
Scheduled
Start: 19 Dec 2014 12:00 PM
End: 22 Dec 2014 12:00 PM
Data Centre
GPN DC Replace Generator
Resolved
Start: 19 Dec 2014 06:00 AM
End: 19 Dec 2014 12:00 PM
PABX
St Lucia Campus Reduced Phone Service
Resolved
Start: 19 Dec 2014 08:16 AM
End: 19 Dec 2014 09:29 AM
PABX
IMB/QBP PABX Service Reduced Due to Storm
Resolved
Start: 18 Dec 2014 06:03 PM
End: 19 Dec 2014 08:44 AM
PABX
Voicemail outage due to storm
Resolved
Start: 19 Dec 2014 08:16 AM
End: 19 Dec 2014 08:43 AM
Internet Services UQ
Brief interruption to UQ Internet connectivity
Completed
Start: 19 Dec 2014 06:30 AM
End: 19 Dec 2014 07:00 AM
Building Networks
Access Switch reloading at OHC cause data outage at Level 6, North.
Completed
Start: 18 Dec 2014 06:00 PM
End: 18 Dec 2014 06:10 PM
Voice Networks
Hazardous work: Prentice ITS VOIP network change
Completed
Start: 18 Dec 2014 07:00 AM
End: 18 Dec 2014 07:30 AM
Single Sign-on Servers
Single Sign-on Identity Provider upgrade
Completed
Start: 17 Dec 2014 09:00 AM
End: 17 Dec 2014 05:00 PM
Data Centre
DC 2 Electrical Power Feeder Commissioning
Resolved
Start: 17 Dec 2014 06:00 AM
End: 17 Dec 2014 04:00 PM
Building Networks
Loss of Internal network connectivity
Resolved
Start: 16 Dec 2014 01:20 PM
End: 16 Dec 2014 04:00 PM
UniFi & SI-net Web Servers
UniFi and SI-net service is affected by network connectivity
Resolved
Start: 16 Dec 2014 01:20 PM
End: 16 Dec 2014 03:42 PM
Data Centre
DC 2 Tie Cable Commissioning
Resolved
Start: 16 Dec 2014 07:00 AM
End: 16 Dec 2014 07:30 AM
Building Networks
Building 26A Human Performance Lab switch reconfiguration
Completed
Start: 15 Dec 2014 05:00 PM
End: 15 Dec 2014 10:00 PM
Data Centre
Gatton DC - RCD Tests
Resolved
Start: 15 Dec 2014 07:00 AM
End: 15 Dec 2014 07:30 AM
Wireless Network
Ipswich Campus Wireless Migration to USQ
Completed
Start: 14 Dec 2014 09:00 AM
End: 14 Dec 2014 06:00 PM
Building Networks
Ipswich Campus Core Network Reconfiguration
Completed
Start: 13 Dec 2014 09:00 AM
End: 13 Dec 2014 06:00 PM
Exchange Mail and Calendaring
Central Exchange Mail Services
Completed
Start: 13 Dec 2014 09:00 AM
End: 13 Dec 2014 01:00 PM
Windows File Serving St Lucia
UQFILE File Serving Services
Completed
Start: 13 Dec 2014 09:00 AM
End: 13 Dec 2014 01:00 PM
SQL Cluster Database Hosting
SQL Database Services
Completed
Start: 13 Dec 2014 09:00 AM
End: 13 Dec 2014 09:30 AM